Meeting Time:
July 21, 2021 at 1:30pm HST
Agenda Item
BFED-76 Misc C6820 WAILUKU CIVIC COMPLEX (BFED-76)
Legislation Text
Contract C6820
County Communication 20-596
Correspondence to Department of Management 09-19-2017.pdf
Correspondence from Managing Director 09-29-2017
Proposed resolutions from Corp Counsel 02-02-2018
Correspondence to Corp. Counsel 02-22-2018
Revised resolutions from Corp Counsel 02-22-2018
Presentation from Erin Wade 03-27-2018
Proposed Resolution from Director of Finance 04-17-2018
Jim Smith 05-15-2018
Correspondence to Corp Counsel 05-16-2018
Correspondence from Corp Counsel 05-17-2018
Diana Kaaihue 10-29-2018
Proposed bills from Budget Director 11-07-2018
Maui Chamber of Commerce 11-08-2018
Correspondence to Budget Director 11-14-2018
Correspondence from Budget Director 11-15-2018
Teri Gorman 12-10-2018
Correspondence to Corp Counsel 03-21-2019
Correspondence from Corp Counsel 03-25-2019
Revised bill from Corp Counsel 03-25-2019
Isadora Sicking 03-23-2019
Ane Takaha 03-25-2019
Correspondence to Managing Director 03-27-2019
Curtis Omuro 03-27-2019
Susan Halas 03-27-2019
Wendy Hudson 03-27-2019
Jen Fordyce 03-28-2019
Everett Dowling 03-28-2019
Sandi Ioakimi 03-28-2019
Grant Howe 03-28-2019
Mike Wildberger 03-28-2019
Jen Mather 03-28-2019
Correspondence from Managing Director 03-28-2019
Terese Masters 03-28-2019
Pamela Tumpap, Maui Chamber of Commerce 03-28-2019
Maile Arensdorf Atay 03-28-2019
Mille Kohl 03-28-2019
Correspondence from Mayor Victorino 03-28-2019
Mary-Allana Holmes 03-28-2019
Marc Tolliver 03-28-2019
Patricia Goff-Williams 03-28-2019
Linda Trageser 03-28-2019
Kristin Holmes 03-28-2019
Bonnie Newman 03-28-2019
Debra Greene 03-28-2019
John Naylor 03-28-2019
Ashlie McGuire 03-28-2019
Connor Logsdon 03-28-2019
Gabe Johnson 03-28-2019
Erika Pless 03-28-2019
Ron Hansen 03-28-2019
Steve Forman 03-29-2019
Claudia Rosenbaum 03-29-2019
William Greenleaf 03-29-2019
Lehua Simon 03-29-2019
Doug Wright 03-28-2019
Tomas and Joan Heartfield 03-28-2019
Noenoe Lindsey 03-29-2019
Robin Knox 03-29-2019
Liko Wallace 03-29-2019
Michael Tengan 03-29-2019
Kent Gorg-Carter 03-29-2019
John Franey 03-29-2019
Kelly McHugh 03-30-2019
Lindsey Gomes 04-01-2019
Correspondence to Managing Director 04-02-2019
Damien Pires 04-03-2019
Paul Hutchinson 04-03-2019
Mariah Dagupion 04-08-2019
Joann Texeira 03-29-2019
Saedene Ota 03-29-2019
Farron Cabral 03-29-2019
Morgan Gerdel 03-29-2019
Nick Drance 03-29-2019
Jonathan Starr 03-29-2019
Joe Myhand 03-29-2019
Joseph Blackburn 03-29-2019
Copy of letter from Committee Chair 03-29-2019
Document from Managing Director 03-29-2019
Brochure from Erin Wade 03-29-2019
Handout from Committee Chair 03-29-2019
Copy of Contract No. C6659
Document from Committee Chair 03-29-2019
Correspondence to Managing Director 04-02-2019
Correspondence to Managing Director 06-06-2019
Correspondence to Managing Director 06-12-2019
Correspondence from Deputy Managing Director 07-30-2019
Correspondence from Managing Director 08-19-2019
Correspondence from Managing Director 08-19-2019 (Exhibit A_001 - PHASE 1B - 100 percent FINAL DESIGN - DRAWINGS) - Part 1
Correspondence from Managing Director 08-19-2019 (Exhibit A_001 - PHASE 1B - 100 percent FINAL DESIGN - DRAWINGS) - Part 2
Correspondence from Managing Director 08-19-2019 (Exhibit A_001 - PHASE 1B - 100 percent FINAL DESIGN - DRAWINGS) - Part 3
Correspondence from Managing Director 08-19-2019 (Exhibit A_001 - PHASE 1B - 100 percent FINAL DESIGN - DRAWINGS) - Part 4
Correspondence from Managing Director 08-19-2019 (Exhibit A_001 - PHASE 1B - 100 percent FINAL DESIGN - DRAWINGS) - Part 5
Correspondence from Managing Director 08-19-2019 (Exhibit A_001 - PHASE 1B - 100 percent FINAL DESIGN - DRAWINGS) - Part 6
Correspondence from Managing Director 08-19-2019 (Exhibit A_002 - PHASE 1B - 100 percent FINAL DESIGN - PROJECT MANUAL) - Part 1
Correspondence from Managing Director 08-19-2019 (Exhibit A_002 - PHASE 1B - 100 percent FINAL DESIGN - PROJECT MANUAL) - Part 2
Correspondence from Managing Director 08-19-2019 (Exhibit A_002 - PHASE 1B - 100 percent FINAL DESIGN - PROJECT MANUAL) - Part 3
Correspondence from Managing Director 08-19-2019 (Exhibit A_002 - PHASE 1B - 100 percent FINAL DESIGN - PROJECT MANUAL) - Part 4
Correspondence from Managing Director 08-19-2019 (Exhibit A_003 - PHASE 1B - ELEVATION 1 - PILI)
Correspondence from Managing Director 08-19-2019 (Exhibit A_004 - PHASE 1B - ELEVATION 2 - CHURCH)
Correspondence from Managing Director 08-19-2019 (Exhibit A_005 - PHASE 1B - ELEVATION 3 - MAIN STREET)
Correspondence from Managing Director 08-19-2019 (Exhibit A_006 - PHASE 1B - ELEVATION 3 - PROMENADE)
Correspondence from Managing Director 08-19-2019 (Exhibit A_007 - PHASE 1B - ENLARGED SITE PLAN - CHURCH)
Correspondence from Managing Director 08-19-2019 (Exhibit A_008 - PHASE 1B - ENLARGED SITE PLAN - PARKING GARAGE)
Correspondence from Managing Director 08-19-2019 (Exhibit A_009 - PHASE 1B - ENLARGED SITE PLAN - UPPER VINEYARD)
Correspondence from Managing Director 08-19-2019 (Exhibit A_010 - PHASE 1B - FLOOR PLAN - LEVEL 1A)
Correspondence from Managing Director 08-19-2019 (Exhibit A_011 - PHASE 1B - FLOOR PLAN - LEVEL 1B)
Correspondence from Managing Director 08-19-2019 (Exhibit A_012 - PHASE 1B - FLOOR PLAN - LEVEL 2)
Correspondence from Managing Director 08-19-2019 (Exhibit A_013 - PHASE 1B - FLOOR PLAN - LEVEL 3)
Correspondence from Managing Director 08-19-2019 (Exhibit A_014 - PHASE 1B - LANDSCAPE PLAN AND SECTION)
Correspondence from Managing Director 08-19-2019 (Exhibit A_015 - PHASE 1B - LANDSCAPE PLAN)
Correspondence from Managing Director 08-19-2019 (Exhibit A_016 - PHASE 1B - LANDSCAPE SECTIONS)
Correspondence from Managing Director 08-19-2019 (Exhibit A_017 - PHASE 1B - MATERIAL BOARD)
Correspondence from Managing Director 08-19-2019 (Exhibit A_018 - PHASE 1B - RENDERING 1 - PILI + PROMENADE)
Correspondence from Managing Director 08-19-2019 (Exhibit A_019 - PHASE 1B - RENDERING 2 - PROMENADE ENTRANCE)
Correspondence from Managing Director 08-19-2019 (Exhibit A_020 - PHASE 1B - RENDERING 3 - CHURCH ENTRANCE)
Correspondence from Managing Director 08-19-2019 (Exhibit B - Wailuku Civic Hub Finance Plan (11.05.2018 DRAFT)_1)
Correspondence from Managing Director 08-19-2019 (Exhibit C - Wailuku Parking Town Study and Mgmt Plan Analysis (05-31-2011))
Correspondence from Managing Director 08-19-2019 (Exhibit D - Parking Action Plan (February 2018)) - Part 1
Correspondence from Managing Director 08-19-2019 (Exhibit D - Parking Action Plan (February 2018)) - Part 2
Correspondence from Managing Director 08-19-2019 (Exhibit E - Wailuku Civic Hub TIAR Draft Final (06-21-2018))
Correspondence from Managing Director 08-19-2019 (Exhibit F - Wailuku PEF Programming Feasibility Assessment (07-21-2017))
Correspondence from Managing Director 08-19-2019 (Exhibit G - Wailuku Campus Space Study (January 2009))
Testimony from Maui Chamber of Commerce 08-20-2019
Testimony from Daralyn Miline 08-20-2019
Testimony from Bryce Ellory 08-21-2019
Testimony from Terese Masters 08-21-2019
Testimony from Kristin Holmes 08-21-2019
Testimony from Yvette Celiz 08-21-2019
Testimony from Jon Woodhouse 08-21-2019
Testimony from Jonathan Starr 08-21-2019
Testimony from Melo Partisano 08-21-2019
Testimony from Elizabeth McDonald 08-21-2019
Testimony from Kathy Corcoran 08-21-2019
Testimony from Barbara Mosle 08-21-2019
Testimony from Erika Lechuga DiSalvo 08-21-2019
Testimony from Barbara Barry 08-21-2019
Testimony from Marc Tolliver 08-21-2019
Testimony from Ilima Smallwood 08-22-2019
Testimony from Terri Erwin 08-22-2019
Testimony from Nick Drance 08-22-2019
Testiimony from Chas Mo 08-22-2019
Testimony from Alena Ornellas 08-22-2019
Testimony from Dierl Bagusto 08-22-2019
Testimony from Sunny Savage 08-22-2019
Testimony from Francine Aarona 08-26-2019
Correspondence to Corp. Counsel 08-28-2019
Correspondence to Managing Director 08-28-2019
Correspondence from Committee Chair 08-27-2019 (aggregate costs)
Presentation from Finance 08-27-2019
Brochure from Dept of Management 08-22-2019
Project costs to date from Dept of Management 08-27-2019
Proposed amendment to Bond bill from Committee Chair 08-27-2019
Testimony from Marc Tolliver 08-27-2019
Testimony from Terri Erwin 08-27-2019
Testimony from Deborah McMenemy 08-27-2019
Correspondence from Managing Director 08-30-2019
Testimony from Jeffrey Andrews 09-04-2019
Testimony from Lopaka White 09-05-2019
Testimony from Daralyn Milne 09-05-2019
Correspondence to Managing Director 09-17-2019
Correspondence from Managing Director 09-19-2019
Report on financing the Wailuku Parking Structure from Cost of Government Commission 11-17-2020